30m × 50m Air‑Supported Membrane Building – Multi‑Sports Training Centre

August 5, 2026
ultimo caso aziendale circa  30m × 50m Air‑Supported Membrane Building – Multi‑Sports Training Centre  0
Background

The city’s outdoor athletics and football fields are unusable for five months each year due to heavy snow and sub‑zero temperatures. Local sports clubs – including basketball, badminton, and futsal teams – have long requested an indoor training facility, but a conventional steel‑frame building would take 12–18 months to construct and exceed the available budget.

The Sports Bureau needed a temporary but durable indoor space of approximately 1,500 m² that could be:

  • Operational within 8 weeks (before the first snowfall)
  • Column‑free to accommodate multiple full‑size courts simultaneously
  • Energy‑efficient for winter heating
  • Relocatable in case the park was redeveloped in the future
  • Weather‑resistant against heavy snow loads and strong winds
The Challenge
Challenge Implication
Short construction window Only 6–8 weeks available before winter
High snow load Local snow load requirement: 0.75 kN/m² (above standard)
Low temperatures Operating down to ‑25°C; need condensation control and heating
Multi‑use layout Need space for 3 badminton courts + 1 basketball half‑court + spectator area
Future relocation Building may need to be moved after 3 years; permanent foundation not feasible
The Solution

The Sports Bureau selected the 30m × 50m Air‑Supported Membrane Building with the following customisations:

Parameter Specification
Size 30m wide × 50m long (1,500 m²)
Centre height 10 m – enough for badminton and basketball clears
Side clearance 5.0 m
Membrane Double‑layer PVC‑coated polyester with thermal insulation liner
Snow load design 0.75 kN/m² (engineered for local conditions)
Wind resistance Designed for 30 m/s gusts
Internal pressure 250 Pa normal, boosted to 350 Pa in snow mode
Fan system 2 × redundant variable‑frequency fans + diesel backup generator
Heating Integrated ducted air‑heating system connected via pre‑installed HVAC interfaces
Hanging points Grid at 4 m spacing, 30 kg capacity each – for LED sports lighting and scoreboards
Entrance Double‑door air‑lock system with a 4.8m wide main door for equipment access
Fire rating EN 13501‑1 B‑s1,d0

The building was delivered in 5 modules (each 10m long) from the factory, along with the fan units, anchoring rails, and all door sets. On‑site installation required only a prepared concrete strip foundation (pre‑cast kerbs with clamping grooves) – no heavy piling or steel columns.

Deployment
  • Week 1–2: Foundation preparation and anchoring rail installation.
  • Week 3: Membrane modules delivered and unrolled; seams welded on‑site.
  • Week 4: Fan units, control system, and HVAC connections installed.
  • Week 5: Inflation and pressure testing; interior lighting and court markings installed.
  • Week 6: Final inspection and handover – fully operational in 6 weeks, beating the snowfall by 10 days.

The double‑layer membrane with insulation kept the internal temperature at a stable +16°C even when outside temperatures dropped to ‑22°C, with heating costs 30% lower than a conventional tent structure.

Results
Metric Outcome
Construction time 6 weeks (vs. 14+ months for steel building)
Total cost 55% less than a permanent structure
Space utilisation 1,500 m² column‑free – accommodated 3 badminton courts + 1 basketball half‑court + bleachers for 150 spectators
Winter performance Withstood 3 heavy snowfalls (>40 cm) with no structural issues; snow slid off naturally due to membrane tension
Condensation control Double‑layer membrane + fresh air system eliminated dripping, even during high‑intensity training
User satisfaction 95% of athletes rated lighting and comfort as “excellent”
Energy consumption Heating and fan energy within budget – no unexpected costs
Key Outcomes
  1. Rapid Community Impact – The centre opened just in time for winter leagues, allowing 12 local teams to train indoors for the first time. Participation in winter sports increased by 40% that season.
  2. Financial Viability – The low initial investment and affordable operating costs made the project feasible without central government subsidies. The building is expected to pay for itself within 3 years through rental fees.
  3. Future‑Proof Flexibility – The modular design means the building can be dismantled, moved to another site, or expanded to 60m length by adding two more modules if demand grows.
  4. Reliability in Extreme Weather – The redundant fan system and backup generator ensured continuous operation even during a 3‑hour power outage caused by a storm – the building never deflated.